Dismantling projects: one factory price shared over its items
Buy a factory for one price, share it over each item, put dismantling costs and mechanic wages into item costs, and read the profit of each factory.
On this page
Dismantling Projects records a factory bought for one price and then taken apart. The price is shared over each machine and item, dismantling costs and mechanic wages raise the cost of the goods they are for, and Reports → Dismantling Project Profit and Loss shows the result of each factory. The goods are sold like any other goods.
This is an extra feature. If the menu is missing, contact the Vende team to turn it on. Its costs are recorded like Purchase Costs, which needs no switch of its own.
1. Record the factory and its items
In Transactions → Dismantling Projects, press Create. Fill in the factory name, seller, location and Price shared by:
- Expected sell price: an item expected to sell for more gets a larger share. The most usual.
- Weight: suits scrap and metals.
- A figure typed per item: you write a figure per item and the price is shared by it.
List the items one row per item: name, quantity, weight and the expected sell price of the whole row. An item already in Master Data → Products, such as scrap by the kg or pipe by the metre, is picked in Existing item, and its quantity is in that product's unit. Offer price may be filled in to compare with the total of the expected prices.
Fill in the Specifications of each item if useful (material, size, pressure, length; one per line, free text): the search box of the project list searches them, so "10 bar" or "stainless" finds the factory that has such a unit. The photo of a unit is kept on its product card (Master Data → Products) once the factory is bought. After buying, specifications are changed with the Unit Specifications button.
The cost of looking at a factory that is not bought yet (transport, an engineer's fee, a permit to enter) is recorded with Record Survey Cost on the project page. It becomes an expense of the shop in the category Factory Survey Costs and stays visible in the Survey costs part of that project, also when the factory is never bought and set to Cancelled.
2. Buy Factory
On the project page, press Buy Factory. Fill in the Price of the whole factory, the supplier (the factory seller) and a cash account if anything is paid now. Fill in Paid now and the payment method when only part is paid (empty means in full). What is not paid becomes a debt to the seller. Vende then:
- shares the price over the items to the cent, so all the shares add up exactly to the price,
- makes a product for each item that has none, with stock to match its quantity, and
- writes one purchase note in Transactions → Purchases.
An item without a figure for the chosen basis gets no share of the price, but can still be given a cost of its own (see Costs). A purchase with VAT and a note discount are entered on its purchase note as usual and are kept when the price is shared again. If the price of a line is changed directly on the note, Add Found Items refuses and names the item and its share: set the line back to that share first, so the correction is not overwritten. A factory of another branch is bought at its own branch.
If the seller also sells the land or the building and the Fixed Assets feature is on, open Land and buildings bought too in the same form: enter a name, the price, the salvage value, the life and the cash account that pays for it. The price is recorded as a Fixed Asset, apart from the price of the machines, and is not shared over the items. For land, enter a salvage value equal to its price so it is not depreciated.
3. Found items
Add Found Items adds what turns up while dismantling. The purchase price of the factory does not change, so it is shared again over all items and the items already there get a smaller share. The cost of goods already sold is worked out again. The earlier share stays visible in each item's history. The button is not there before the factory is bought or once the project is Finished.
4. Costs
Record Cost records crane, truck, dismantling gang, warehouse rent, spare parts bought or a repair wage. Fill in the description, the amount and who pays: a cash account, or a supplier when it is not paid yet (a debt to the mechanic or the crane owner).
- With no item picked, the cost is shared over all items by their value.
- With items picked in Only for items, the cost stays on those items, also after the price is shared again.
A wrong cost is corrected or deleted by pressing its number in the Costs list on the project page; the cost of the goods follows. An item without a share of the price can be given a cost of its own, shared by quantity.
A cost raises the cost of the goods and the stock value, and its journal is Debit Inventory, Credit the cash account or Trade Payables. Several costs to the same mechanic are paid at once in Transaction Details → Purchase Payments.
A monthly mechanic's pay is not a cost per item: record it as a Salary expense or through Payroll.
5. Moving cost between items
Three buttons on the project page move cost without money moving. The project's total cost and the books do not change, only the cost of each item in the Stock Card.
- Fit Spare Part: a spare part from the shop's stock (for example a bearing) is fitted to one unit. It leaves stock at its average cost and the unit's cost goes up by that. If the part's cost changes later, the unit's cost follows. Items with serial numbers cannot be used as spare parts yet.
- Cannibalise Between Machines: a part is taken from one unit to fit another. Enter what the part is worth: the cost of the unit it comes from goes down, the cost of the other goes up. A unit cannot give more than its cost.
- Split Unit: one unit (for example an industrial UPS) is taken apart into parts sold separately (the battery). Each part becomes a new item with the cost you give it, taken from the unit's cost. The rest stays on the unit, or choose Rest becomes scrap to move it to a scrap item and take the unit out of stock.
Every move shows in Cost moves on the project page with its source, destination and value, so where each part came from can be traced.
Rules that protect the figures: a unit already sold (in part or whole) cannot give or take cost, because the sale that already happened would change its cost. Split Unit with the rest becoming scrap works only when the warehouse holds no other stock of the same product. Adding a found item that would leave a unit with less than the cost it already gave away is refused, naming the unit. A spare part fitted by mistake is undone with Undo Spare Part; its stock adjustment cannot be deleted alone.
6. Selling
The goods are sold at the till or on a sale note. A good not repaired yet can be ordered with a down payment in Transactions → Sales Orders. A buyer who cancels: cancel the order, then choose whether the down payment is forfeited or refunded.
7. The Dismantling Project Profit and Loss report
Reports → Dismantling Project Profit and Loss shows each factory bought: purchase price, costs, cost basis, sales and cost of goods in the period, the profit on what was sold, the value still on the shelf and how much of the cost basis has come back. The figures are the same as the Profit by Item report, and the cost basis of a factory is counted in full, not only in the period. An item shared by several factories, for example scrap by the kilo, has one stock: its stock and sales count to the factory bought first, so all factories add up to the stock ledger. Filter by Status to see only the factories just bought, the ones being dismantled, or the finished ones.
Good to know
- One item is one product with stock 1: its cost is read per item, not averaged with other items.
- A factory already bought cannot be deleted because its purchase note is already in the books.
- The purchase note of a factory cannot be deleted or voided while the project exists, because the project's goods came into stock through it. Its contents may be changed.
- A buyer's forfeited deposit stays other income in the profit and loss and is not part of a factory's profit in the report.
- Investor or partner money per factory has no feature of its own: record the money as a Loan or Capital and share the profit from the project report.
- The learning path for the team is in the Factory dismantling and reconditioning guide.